The scope of work for this project consisted of new concrete construction for the facility. The early concrete works for the facility included two octagon shaped tank foundations, two concrete pit structures, a retaining wall and a building foundation. In total 1,060 m3 of concrete and 200,000 kg of rebar were placed for these structures.