Located on Hwy 63 in Fort McMurray, this project involved replacing an exterior girder damaged by a high load. The scope of work also included replacing all three deck joints and casting a new sidewalk atop the girders. The damaged girder was successfully demolished in a single night. A new box girder was then fabricated and erected using two cranes. Additionally, a complete hoarding was erected on the bridge deck to cast the sidewalk and reinstall the bridge rails.